Atlantic City Not Playing Games with its Wastewater System
Beautiful beaches punctuate the New Jersey coastline, but while sand is welcomed and appreciated along the ocean’s edge for visitors, it can wreak havoc on the pipes that comprise a community’s wastewater collection system. The Atlantic County Utilities Authority (ACUA) struggled with this firsthand when a critical force main line connecting three shoreline communities to the wastewater treatment plant began to fail.
The original 30-in. diameter, welded-steel force main that conveys wastewater from the towns of Ventnor, Longport, and Margate — a region referred to as Down Beach — was installed in the mid-1970s. It extends north from the Down Beach area toward the treatment facility. Along the way, it passes through a former municipal airstrip, Bader Field, under a navigable waterway called Beach Thorofare, and beneath both the Atlantic City Expressway and the New Jersey Transit train lines that run between Atlantic City and Philadelphia.
RELATED: No Gamble Here: HDD a Success in Atlantic City
By the 1990s, the steel pipe began exhibiting signs of deterioration due to an excess of sand and grit in the system. “We’re a beach community,” said ACUA chief engineer Tom Ganard. “And we get a lot of beach sand coming into our system through various means — street manholes, infiltration, people coming off the beach and taking showers — and this grit runs through the line. It was literally wearing a groove in the bottom of the steel pipe.”
The 30-in. diameter HDPE PE 4710 pipe enters the HDD path to go under the Beach Thorofare waterway.
Photo courtesy of ACUA
After a series of failures in the line, the Authority sliplined a portion of the steel main coming from the Down Beach area up to Bader Field. But in 2017, the worst-case scenario unfolded. “I can remember exactly where I was on Sept. 23, 2017, when I got the call that you never want to get,” said Joe Pantalone, vice president of ACUA’s Wastewater Division. “That was the first main break of Bader Field.”
The ACUA acted quickly to bypass the line but it was only a temporary solution. The Authority knew it was on borrowed time and began the design and permitting process for the total replacement of a mile and half of force main. “Once we knew that we had problems in that one area, we immediately decided to replace the entire Bader Field main,” said Pantalone.
ACUA’s troubles weren’t over just yet. While in the design and permitting process, another catastrophic failure occurred in 2019, just south of the previous break. This kicked the project into overdrive, and the ACUA secured advanced permission to move forward with the total replacement it had already been planning.
The $8 million replacement project was divided into two phases: the first was the replacement of the Bader Field main line using a standard open-cut construction. This phase was completed in 2020 by Arthur R. Henry Inc. (Egg Harbor Township, New Jersey)
The second phase, which was not in failure mode but was part of ACUA’s master plan, is the portion running under Beach Thorofare, the Atlantic City Expressway, and the New Jersey Transit lines. General contractor C. Abbonizio Contractors (Sewell, New Jersey) used horizontal directional drilling (HDD) for this section, including the formidable 1,500-lf underwater segment.
RELATED: Two Platforms, Two Shore Approaches, Two Lines… and a Hurricane
For the HDD portion, the Abbonizio crew did a smaller 8-in. diameter pilot hole drilled to establish the bore path direction. At the point where it comes out of the ground, the crew reattached a larger-diameter bore — in this case, a 42-in. drill —and then pulled it back through the same path, making the hole the size needed for the HDPE pipe replacement. Then, the new pipeline was pulled through the opening.
C. Abbonizio subcontracted the HDD portion to Michels Corp., a family-owned and operated energy and infrastructure construction company headquartered in Brownsville, Wisconsin. The drill rig was a Uni 250×400 with a pulling force capacity of 250,000 lbs and a torque capacity of 40,000 ft-lbs.
The directional boring was completed in June 2021 and only took a few days. The accuracy of the drill was nothing short of amazing. “They literally hit the survey stake that was more than a thousand feet away that they had put in the ground at the exit point,” said Ganard. “Now, the pipe just needs to be connected to the current system on both sides.
“One of the benefits of using directional drilling is that it minimizes disruption to not only marine activity on the waterway but also the channel bed, water, and aquatic plants and animals in the bay. “The whole project is working in an environmentally sensitive area,” Ganard noted. “So, the fact that we could do the directional drilling really saved a lot of environmental disturbance that could be related to a construction project.” After installation, the pipe was approximately 80 ft below the Beach Thorofare.
“The entire process amazed me,” said Nicholas Listner, with the engineering department of C. Abbonizio. “More specifically, watching them track the pipe as it was drilled was definitely the most interesting part for me. There was a team guiding the drill head from an office. They knew where the pipe was at all time — both the location and the elevation.”
The HDD path for the HDPE pipe under the Atlantic City Beach Thorofare waterway. Photo courtesy of ACUA
For both phases of the Down Beach force main replacement project, HDPE pipe was the material of choice. The 30-in. HDPE DIPS has an outside diameter of 32 in.
“We knew HDPE was a good solution for [this project] where we’re running at 60 psi,” Ganard said. “We had used it approximately 20 years earlier in another portion of our system, and when we inspected it, we did not see any signs of wear. We were comfortable that this pipe would have much better characteristics for what we’d be putting through it.”
According to the Plastics Pipe Institute, Inc. (PPI), the pipe can be used in methods of underground installation such as HDD or open cut. PPI is the major North America trade association representing the plastic pipe industry.
“A recent industry survey showed that HDPE pipe continues to be the most common type of pipe used in trenchless installations,” offered Camille George Rubeiz, P.E., F. ASCE, senior director of engineering for the Municipal and Industrial Division of PPI and is also the co-chair of the HDPE Municipal Advisory Board. “Properly designed, installed and fused, HDPE has a 100-year design life, zero allowable leakage, largest internal diameter and is the best water piping solution for open cut and trenchless installations. Plus, it has a larger flow capacity per PPIPACE.com, C coefficient of 150 — up to 50 percent higher C than others, corrosion and tuberculation resistance, lowest initial cost and lowest life cycle cost.
RELATED: Large Diameter HDPE Solves Deep Combined Sewer Overflow in King County, Washington
“The prevention of infiltration was one of the key benefits of the pipe here in Atlantic City. But a critical factor was also taken care of and that was because of the HDPE pipe’s inherent resistance to salt water. Plus, it has resistance to water hammer, fatigue, ground movements, freezing temperatures and earthquakes.”
According to Listner, several HDPE pipe companies were used on this project. The pipe was produced by Performance Pipe (Plano, Texas), a division of Chevron Phillips Chemical Company LP. A McElroy Mfg. Inc. (Tulsa, Oklahoma) Trackstar 900i butt fusion machine was used to join the straight pipe ends. The 45- and 11.5-degree bends were manufactured by GF Central Plastics LLC. (Shawnee, Oklahoma). Electrofusion couplings were produced by Integrity Fusion Products Inc. (Peachtree City, Georgia)
“The Down Beach force main replacement project is a massive undertaking that will resolve decades of challenges with a deteriorating steel pipeline. But for ACUA, it’s much more than that. “No one pays attention to the Wastewater Division until there is a failure,” said Pantalone. “This shows the community that we are diligent in our reinvestment into our infrastructure, we stopped the bleeding as quickly as we could, and we didn’t stop there. We really went the extra mile to carry out what we are pledged to do by replacing the entire main.”
Steve Cooper is managing director with SCA Communications.