Robbins Double Shield Achieves Powerful Progress in Russia
March 30, 2012
“The Robbins TBMs have proven to be very reliable machines and thanks to the correct selection of these machines we were able to finish the tunnels on time. This was in spite of the fact that construction risks, as assessed by geologic testing, were extremely high,” said Vladimir Fedukin, deputy manager of project owner DCRC-Sochi.
The newly rebuilt Robbins TBMs were designed for the difficult conditions with low profile muck buckets and radial scoops for improved face stabilization. The design also included replaceable bucket lips and injection ports, allowing foam additives to be used through the cutterhead for ground treatment. These features enabled the machines to pass through numerous fault zones.
In May 2010, the 6.3-m (20.3 ft) machine was stopped after encountering a significant fault zone consisting of broken rock and running soft ground. Field service personnel and crew successfully freed the machine by excavating a bypass tunnel around the TBM cutterhead. Following the restart, a combination of continuous probe drilling and ground treatment with cement silicate and foam kept the machine moving forward. Excavation with the 10-m (32.8 ft) machine was similarly aided by continuous probing and ground treatment.
The extensive infrastructure project for DCRC-Sochi (a subsidiary of Russian Railways), provides road and railway routes between the small town of Adler on the Black Sea and the mountain resort of Alpika, with a scheduled completion date of June 2013. The new lines will also connect to the M-27 highway, improving infrastructure in the region.
This article was submitted by The Robbins Co.