Kansas City Water Services Turns to Spirally Wound Relining to Rehab Circular Brick Combined Sewer

Kansas City Water Services desired to rehabilitate a 125-year-old original 114-in. circular brick combined sewer due to its age, deterioration and deflection.

Ultimately, a crack had formed in the crown of the structure, affecting the structural integrity of the pipe. The sewer rehabilitation project at 22nd Street & Paseo — under four lanes of heavy duty traffic — is located in the heart of Kansas City, Mo., along the Paseo Parkway.

Design considerations had to include not only sheer size, but many other challenges such as depths up to 35 ft from surface to invert, flow levels averaging 10 to 14 in. during normal operations, bypass pumping (technology dependent), storm surcharging, soil considerations, slope, limited access and two sweeping 90 degree bends with tight radii.

before

before



Various technologies were included in the initial assessment, such as: Shotcrete, CIPP, CCCP, FRP sliplining and SPR. Each technology had their particular strengths and weaknesses in regards to maintaining 100 percent of the existing capacity, fully structural design and provide a 50-year solution. The final approved technologies were CCCP, sliplining and SPR.

After

After


Getting Started


The project was competitively bid in February 2014 with an anticipated start for mid-summer of that year. Before award of contract was granted, a third party stamped design was provided by Brierley Associates to KCMO for the SPR technology. Once the submitted design was received, reviewed and approved by KCMO Water Services, SAK Construction LLC was issued a firm contract and a formal notice to proceed. As a result, construction started in late August 2014. The Sekisui process uses a PVC-based material that is spirally wound into an existing pipeline. Successive wraps of profile are locked together and the annular space between the wound profile and host pipe is grouted. The result is a strong composite pipe integrated with the existing pipeline.

The SPR design called for the installation of a 100-in. ID SPR 102SRW liner with steel reinforcement that is integral within the profile. The primary reason behind using the 100-in. ID liner was due to internal dimensions of the host varying from 108.5 in. to 114 in. with significant deflection at the 4 o’clock and 7 o’clock positions in the crown of the pipe. The dimensions were verified by SAK, using laser profiling equipment, taken every 4 ft. By using the SPR process, the cross sectional loss still increased existing flow capacity, while also providing a fully structural 50-year solution.

Weather Challenges


As construction progressed, another encounter was faced head on: Mother Nature. On three separate occasions, SAK personnel were forced to exit the pipe due to rising water from thunderstorms within that particular basin. SAK and KCMO developed and synchronized a communication network between local and national weather services, and the KCMO storm alert system was able to determine when they could safely enter and exit the pipe. Once the storm alert was signaled, SAK would secure the SPR winding machine to the host, cut the PVC profile, remove all ancillary items and safely exit the pipe. After the event had passed and water subsided to manageable levels, the machine was cleaned, profile was re-fed into the machine and construction continued.

The successful winding, bracing and grouting of the 100-in. SPR profile occurred in a continuous live combined sewer through two tight, opposite 90 degree bends. This was completed through existing manhole structures and one new access that the owner required. Matt Thomas of KCMO said, “This was the first for us in Kansas City, using the SPR product. We are very pleased with the performance of the contractor and of the product during the installation process of the project. We look forward to use this type of trenchless technology installation for future projects.”

KCMO also noted that, due to the small footprint and not having to open additional access locations, there was very minimal interruption to traffic flow on the Paseo Parkway. The traffic control on 22nd Street was limited to one lane closure for less than two weeks over a 200-ft section while the profile was being fed down the existing manhole.

The project was completed on time, on budget, while having nearly zero impact on the local community. Most importantly, SAK and Sekisui were able to provide the fully structural, 50-year design with improved hydraulic flows for the 125-year-old combined sewer.
Brent Adams is SPR division manager at Sekisui SPR Americas LLC.
// ** Advertisement ** //

See Discussion, Leave A Comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.