CIPP Used to Reline Capitol Conduit
April 26, 2011

The new visitor center extends from the Capitol to the Library of Congress. During the construction, 114-ft vertical, galvanized electrical conduits were installed. The purpose of these conduits was to supply a series of electrical wires 40 ft underground to power a series of security and other electrical equipment within the Capitol Visitor Center (CVC). Shortly after the installation of the conduits, groundwater started to seep in at the joints.

Secondly, the wires that were incased by the galvanized conduits were at risk to be damaged by the groundwater and could fail at any time, which could shut down the CVC security system.
Finally, due to the sensitivity of the area absolutely no excavation was possible. The vault that housed all 11 conduits was no more than a 100 yards from the actual Capitol building.
Solution
A time frame of less than three days was also in place once the project was started because of security and the fact that the Capitol Visitor Center was already open and was housing events each day. A light weight, fast pipelining system that would not create any harmful odors in order to not disturb visitors was needed. Dynamic Drain went with its Perma-Liner pipe lining technology.
This would allow Dynamic Drain to install an epoxy felt liner within the broken initial diameter of the conduits. The liner was a good idea because it barely reduced the initial diameter of the conduit and it would be a seamless brand new structural pipe from end to end. This would allow the electrical contractor to string new wires without the risk of getting caught on joints and stripping the wires. The Perma-Liner Inversion System allowed Dynamic Drain to install four liners a day in order to meet the Capitol Visitor Center’s time requirement of three days. The 100 percent solids epoxy created no alarming odors.
This article was supplied by Perma-Liner Industries.