Long HDD Bore for the Garzweiler Mines

Foltin is a casual character, well known for his phlegmatic calmness, but also for his knowledge and experience. He has been with REVOR since 2005 and is experienced with the GRUNDODRILL 15 N, manufacturered by TRACTO-TECHNIK, Lennestadt, Germany. REVOR have been acquainted with the HDD bore technology since 1999.
“We have grown with every task and the challenges have become part of our everyday businesses. That is why the expertise of the colleagues and good team work are an important success factor, as well as the machine technology,” according to the responsible head engineer Helmut Schürmann.

The new path and also the motorway junction Jackerath are to be moved approximately 1 km further to South-East to start running again from 2017 onward. Then the gigantic bucket-wheel excavators will work on making the A61 “disappear” further westward, which is planned to be rebuilt in 2035. Today, these aspects have to be taken into consideration by RWE power for operation of the brown coal mining plant.
The Bore Task

Execution
The special challenge was in the unusual steep entrance with a 30 percent inclination, to quickly get to a 12 m depth. The data cable then lies at a depth of approximately 5 to 6 m below the future motorway lanes, so that any construction work would not be influenced. The further process beneath the A 61 is carried out horizontally and rises at 17 percent again to the target point, which is at the same height as the starting pit.

To accomplish the pilot bore they chose a bore head, Type Medium Drillhead. The round framed chisel of this head tears the ground open and simultaneously equipped with hard metal to protect against wearing minerals.
The detection and steering was carried out with a Digitrak-Eclipse, which ran perfectly up to depths of approximately 6 m, but from then some passive disturbances occurred. These were probably caused by underground rubbish, which had been disposed during the motorway construction work in the early years. This meant a reverse of the pilot bore and installation of a special depth sonde Eclipse F2, which guaranteed a trouble-free detection and steering process. A TT backreamer with weld-on claws and flow grooves was applied for the two-step expanding process from 115 to 180 and then from 180 to 250 mm.
The cable protection pipe, HDPE 160×14.9, PN 11 from the company Rehau, was connected from partial lengths of 100 m with three butt-welds to produce a 400-m long pipe length and then laid out in the open terrain. Only 3 tonnes pulling force were measured during the pipe installation. The process itself took one day to accomplish and the same time was required for the pilot bore and each expanding process.
The bore and pipe installation work was carried out in difficult weather conditions, starting in the last week of February 2010 and completed on March 2 to the fullest satisfaction of the contractor.
This article was submitted by TRACTO-TECHNIK, headquartered in Lennestadt, Germany.