Installation Honorable Mentions
Enbridge Alberta Clipper & Southern Lights

Work began near Leonard, Minn., and made its way to Superior, Wis. Michels installed 47,600 ft of 36-in. pipe, with installations varying from 1,300 to 5,200 ft for the Clipper.
The Southern Lights project was 30,837 ft of 20-in. pipe, with crossings ranging from 1,000 to 5,200 ft. Michels sent nine of its 14 large capacity drill rigs to work on the project at one time — the first time in Michels’ long history that it has resourced out so many for one contract within a 150-mile radius.
Temperatures ranged from the mid-80s to 20-below F, making the conditions extremely challenging. Additionally, while working on the project, Michels executed three HDD pullbacks in one day.
Project Owner: Enbridge
Engineer: J.D. Hair & Associates
Contractor: Michels Corp.
Microtunneling Under Lake Oahe in South Dakota

Michels had to drill a 110-ft deep caisson with a diameter of 20 ft on the shore to launch the machine. Also, the underwater retrieval of the MTBM became much more difficult with the additional water table depth, forcing Michels to create new plans to retrieve the machine. Aided by A.D. I. Marine Professionals, Michels performed the wet retrieval of the MTBM. The retrieval process took two days, while the entire tunnel took six weeks.