16th DCA-Europe Congress in Usedom, Germany
December 28, 2011
“Highly Developed Drilling, the Strongest Link in the Energy Chain” was the self-confident motto of the congress for which more than 120 participants from Germany and other European countries had signed up again.
When transmission lines for oil, gas, water or electricity are laid this means that crossings of obstacles belong to the most demanding sections of construction. These structures cannot do without trenchless technology or horizontal directional drilling (HDD), was emphasized by DCA-Europe president Hermann Lübbers in his opening address.
Trouble around Certifications
1,224 Km Through the Baltic Sea
The congress focused primarily on the Nord Stream Pipeline, the probably biggest European infrastructural project with a total investment of 7.4 billion Euros. Dr. Dirk von Ameln of Nord Stream AG reported about the completion of the first of two pipeline stretches of 1,224-km through the Baltic Sea, from Russian Wyborg to Lubmin in Mecklenburg-West Pomerania. Through this pipeline with a bore diameter of 1,153 mm, designed for an operating pressure of 220 bars, up to 27.5 billion cu m of gas will stream to western Europe per year. When the second pipeline is completed in the last quarter of 2012, this transport capacity will be doubled again to 55 billion cu m.
The Nord Stream pipeline is the longest pipeline of the world that leads without disruption through compressor stations. The gas will be inducted in Russia with a pressure of 220 bars. The pressure will continuously drop during the transport to Germany. Therefore, the pipeline was laid in three sections with varying wall thicknesses, each dimensioned for a different pressure level – 220, 200 and 170 bars. These three pipeline sections of the first stretch were connected under water in June 2011. The section that started in Russia was welded to the middle one offshore Finland in a depth of about 80 m, the middle section was welded to the section landing in Germany offshore the Swedish island Gotland in about 110-m depth. In August 2011, the remaining water in the pipeline after the pressure tests and welding under water was pumped down. For this dewatering a temporary compressor station was erected in the German landing area. By means of compressed air, a pigging haul was activated that moved at a speed of 0.5 m per second from the German to the Russian landing area. After dewatering the pipeline was dried by compressed air from the German side to get rid of the last moisture on the pipeline’s inner walls.
The diameter of 1.2 m (48 in.) touches the technical limits to lay pipelines on the ground of the sea, emphasized Dr. Georg Nowak of Nord Stream AG, who is project manager for the pipeline construction in the German sector. The project team was confronted with really singular challenges concerning choice of material, methods of laying, pipe routeing, logistics, as well as contract and time management in order to complete the project within the schedule, the planned budget and under consideration of various interests, described Dr. Nowak the determining factors concerning this superlative construction project.
At the landing station in Lubmin near Greifswald, OPAL and NEL take over the gas from the two Nord Stream pipelines. 55 billion cu m of natural gas that are delivered by Nord Stream all together are divided 36 billion cu m per year to OPAL, and 19 billion cu m per year to NEL.
OPAL leads around 470 km from the landing station in Lubmin to Olbernhau in Erzgebirge (Ore Mountains). NEL transports the natural gas over a length of 434 km to Rehden with its gas reservoir. Both pipelines have a diameter of 1,400 mm.
OPAL was finished in June 2011, NEL is currently under construction.
Visit on the Spot
One of the highlights of the congress this year was the visit to the landing station in Lubmin. The participants had the opportunity to have a close look at this intersection of the European gas network that is still under construction.
After 1,200 km sea pipeline the gas is received at this gas transfer station, filtered, pre-warmed, measured and distributed to the two landward pipelines OPAL and NEL. And all this happens in technical dimensions that are unique worldwide.
Another lecture by Willi Peitz, CEO of GWG Grevenbroich GmbH, a client and network operator, described his positive experiences and the advantages of the directional horizontal drilling technique meanwhile indispensable to him when service pipelines have to be laid in intra-urban areas.
Reports about spectacular drillings, like the crossing of the strait Solent in Great Britain on a length of 3,930 m rounded the issue off at the annual congress that can be called a success concerning content and ambience. Hopefully the program quickened some interest in the next annual congress in 2012, true to the motto that after the congress is before the congress. In 2012, the annual congress will be held from Oct. 10-12 in Cambridge, Great Britain.
This article was provided by DCA-Europe executive secretary Dipl.-Geol. Dietmar Quante. For more information about DCA-Europe, visit www.dca-europe.org.